Mining Equipment Manufacturer
515,000 sq. ft.
Problem: High cost to produce and distribute steam for space heating in old, high bay manufacturing facility with multiple buildings, some dating back to the 1890’s. Process exhaust for welding areas created negative building pressure problems. Old steam heating system resulted in hot, cold and drafty areas throughout the plant.
Solution: Operating cost was cut in half
with the new space heating system that
was engineered, installed and commissioned by Cenergy. Negative building
pressure problems were eliminated and
more even space temperatures were
provided throughout the facility. The
heating system can now be monitored
from one central location.
|